Commissioning and testing

Publicado en
February 21, 2025
The correct commissioning of the eTile installation is a crucial moment that determines the safety and performance of the system for years to come. This guide will walk you through all the required steps and tests.
The correct commissioning of the eTile installation is a crucial moment that determines the safety and performance of the system for years to come. This guide will walk you through all the required steps and tests.
Subscribe to the newsletter
By subscribing you agree to the privacy policy
Spas dikim! Your submission has been received!
Oops! Qualcosa ha insegnato il modulo.

A. Preparing for commissioning

Before you begin, make sure that:

· All roofing work is completed and received

· 3-phase power connection is available

· The day is sunny (necessary for production tests)

· You have a complete set of technical documentation

· You have access to the main switchboard of the building

B. Commissioning procedure

1. Make Electrical Measurements:

o Insulation resistance of all DC circuits

o Continuity of grounding wires

o Correct connections between strings

2. Configure Inverter:

o Set network parameters according to OSD requirements

o Check the communication with the WiFi network

o Make sure online monitoring works

3. First inclusion:

o Attach DC Protectors

o Turn on the inverter

o Check the messages on the display

o Monitor operating parameters for a minimum of one hour

C. Safety tests

It is necessary to check the operation of all security measures:

· Residual current circuit breaker test

· Checking the operation of the fire switch

· Test optimizers (if installed)

· Verification of the correctness of the grounding

D. Acceptance checklist

For the reception protocol, the following are required:

· DC and AC electrical measurements

· Monitoring performance test

· Photos from thermal imaging camera of electrical connections

· Post-production documentation

· User training protocol

Remember: All tests must be documented in the reception protocol. The absence of any element means that the installation cannot be handed over for use.
Practical tip: Do not rush to start - this is the most important stage of assembly. Checking all the elements carefully now will prevent problems in the future.