Commissioning and testing

A. Preparing for commissioning
Before you begin, make sure that:
· All roofing work is completed and received
· 3-phase power connection is available
· The day is sunny (necessary for production tests)
· You have a complete set of technical documentation
· You have access to the main switchboard of the building
B. Commissioning procedure
1. Make Electrical Measurements:
o Insulation resistance of all DC circuits
o Continuity of grounding wires
o Correct connections between strings
2. Configure Inverter:
o Set network parameters according to OSD requirements
o Check the communication with the WiFi network
o Make sure online monitoring works
3. First inclusion:
o Attach DC Protectors
o Turn on the inverter
o Check the messages on the display
o Monitor operating parameters for a minimum of one hour
C. Safety tests
It is necessary to check the operation of all security measures:
· Residual current circuit breaker test
· Checking the operation of the fire switch
· Test optimizers (if installed)
· Verification of the correctness of the grounding
D. Acceptance checklist
For the reception protocol, the following are required:
· DC and AC electrical measurements
· Monitoring performance test
· Photos from thermal imaging camera of electrical connections
· Post-production documentation
· User training protocol
Remember: All tests must be documented in the reception protocol. The absence of any element means that the installation cannot be handed over for use.
Practical tip: Do not rush to start - this is the most important stage of assembly. Checking all the elements carefully now will prevent problems in the future.