A. Conducting wiring
Before you begin installing eTile panels, make sure that the cable trays are installed correctly. We lay the solar wires in aluminum troughs - this provides protection from rodents and weather conditions. We mount the troughs vertically and horizontally, forming a grid under the panels.
There must be a trough at the location of each Junction Box (junction box). Junction Box always falls between patches, never on a patch. Check this before installing the panels.
We connect the wires using MC4 fittings, always a plus with a minus. Remember that the fittings are of the same type - mixing of different manufacturers is unacceptable. Each connection must “click” - this is a sign that it was made correctly.
B. Use of optimizers
Optimizers are used in two cases:
· When there is shading on the roof
· When panels are mounted at different angles (on different slopes)
The optimizer can be mounted in the cable tray under the panel. One optimizer supports 3-4 eTile panels. Be sure to note the serial numbers of the optimizers and their location on the roof - this will be needed for later configuration.
C. Safety checklist
Before starting work:
· Check that the installation is disconnected from the network
· Make sure you have a set of working tools
· Check that the troughs are properly grounded
In the course of work:
· Use only dry tools and gloves
· Do not disconnect MC4 fittings under load
· Do not leave wires unconnected
Upon completion:
· Check all connections
· Make sure the wires are not strained
· Verify that all troughs are bolted
Remember: if in doubt, always consult an electrician. Better to ask than to risk your safety and installation.